Customer Success Stories / Realign Flow for Growth

CASE STUDY · TIER 1 AUTOMOTIVE, DRIVETRAIN COMPONENTS

Realign Flow for Growth

The best-performing plant in its network — $130M+ in annual revenue, serving several large strategic customers — still had to find contractually mandated cost savings after the easy gains were gone, while the COO wanted it ready for growth. Here’s how a shift from station-by-station thinking to workflow dynamics found both.

$600K

Direct labor savings, 12+ person shifts

$1M

Opportunity cost savings

$3M

Near-term CapEx avoided, to meet current demand

The Situation

The easy savings were already gone.

This was the best-performing plant in its network — $130M+ in annual revenue, serving several large strategic customers. The COO wanted to improve financial performance while preparing the plant for growth. But the plant manager was stuck: the annual cost savings mandated in existing customer contracts had to come from somewhere, and the low-hanging fruit was already harvested. What was left was more complex, and the risk of getting it wrong was high.

Demand was growing, but rigid automation and a lack of open capacity meant growth looked like it would need roughly $3M in new investment just to keep pace — on top of a savings target the standard continuous-improvement playbook, station by station, had already exhausted.

Before Vayoom

Best-performing plant in its network, $130M+ revenue

18% EBITDA, high indirect cost

Rigid automation, no open capacity for growth

what was in the way

Contractually mandated cost savings, with the easy gains already gone

A ~$3M CapEx ask just to grow into current demand

Complex, high-risk problems the usual playbook had already exhausted

Client Profile

$130M+ revenue, best-performing plant in network

Executive Sponsor

COO, preparing the plant for growth

Diagnostic Method

Product-workflow dynamics, not station-by-station

Prior State

Low-hanging fruit already harvested

The Diagnosis

Why the plant needed a different lens, not more effort

The plant’s continuous improvement program had already wrung out the obvious gains by looking at each station on its own — finding its bottleneck, fixing it, moving to the next. That playbook was tapped out. What was left wasn’t a bottleneck controlled flow problem anymore; it was a flow dynamics problem.

The plant team was guided to think in terms of product workflows and customer focus — the dynamics between stations — rather than the disconnected work happening at each one. That reframing surfaced answers the station-by-station approach couldn’t: buffer sizes and their locations were reevaluated, some work cells were consolidated while others were broken apart — whichever exploited the dynamics and minimized resource use — and scheduling was rebuilt around the workflow, not the individual station.

The Approach

Five steps, in this order

The capacity was already there — it was locked up in downtime, redundant maintenance cycles, and workflows that hadn’t been rationalized in years.

01

Reframe around workflows, not stations

Guided the team to think in terms of product workflows and the dynamics between stations — customer-focused flow, not station-by-station fixes.

02

Analyze uptime and buffers dynamically

Ran a dynamic analysis of machine uptime and evaluated buffer sizes and their locations to find where capacity was actually being lost.

03

Decouple and reschedule

Separated operations that didn’t need to run in lockstep, then rearranged and scheduled work for optimum resource use and financial performance.

04

Reconfigure the work-cells

Consolidated some work cells and broke others apart — whichever exploited the dynamics and minimized resource use — and converted select robots into cobots for greater throughput effectiveness.

05

Cut maintenance-driven CapEx

Rebuilt maintenance policies to reduce the new equipment the growth plan would otherwise have required, and reduced labor use through the redesigned scheduling and workflow.

“For the first time, I could walk into the COO’s office with a specific number and defend it. We’re still using the platform every week — it’s not a one-time study, it’s how we plan and run the floor now.”

— Plant Manager
The Results

What changed on the floor — and on the P&L

The reframe from station-by-station fixes to product-workflow dynamics is what found capacity the plant didn’t know it had — $600K in direct labor savings, $1M in opportunity-cost savings, and roughly $3M in near-term capital avoided just to meet current demand. For growth beyond that, the plant manager now had a specific, defensible CapEx case to bring to the COO — and kept using the platform to plan, produce, and control operations well after the initial engagement.

23%

EBITDA — a 30% improvement

$600K

Direct labor savings, 12+ person shifts

$1M

Opportunity cost savings

5 FTEs

Reduction in overtime

$3M

Near-term CapEx avoided, to meet current demand

Increased production flexibility and scheduling

Specific growth CapEx needs, clearly defined for the COO

Ongoing use of the Vayoom platform to plan and run the floor

Workflow stoppage hours, before & after Total stoppage hours by workflow station — the same equipment, running far less idle. 600 450 300 150 0 WF 0 WF 3 WF 4 WF 5 WF 6 WF 8 WF 10 Workflow station Before After
AUTOMOTIVE · SAFETY-CRITICAL PARTS

Met Demand at Lower Cost

$2.5M in operating cost savings plus a 39% increase in net income

Read the full story →
AUTOMOTIVE · DRIVETRAIN AXLES

Increased Flow & Flexibility

$752K in net operating cost savings, plus a 1,139% return across the project

Read the full story →
MANUFACTURING SME · POST-BANKRUPTCY

Bankruptcy to Profitable

90 days to cash-flow positive, late shipments cut from $1M to $92K

Read the full story →
Vayoom Vantage — Profit Potential Simulation

See what closing the gap is worth — in dollars.

A free no-obligation profit potential projection, built from your actual operational data with Vayoom Vantage. Not a demo. Not a pitch. A projection.

No obligation. Data-driven projections. Zero commitment.